The ITCertKing Microsoft 070-178 exam questions is 100% verified and tested. ITCertKing Microsoft 070-178 exam practice questions and answers is the practice test software. In ITCertKing, you will find the best exam preparation material. The material including practice questions and answers. The information we have could give you the opportunity to practice issues, and ultimately achieve your goal that through Microsoft 070-178 exam certification.
ITCertKing is a website to meet the needs of many customers. Some people who used our simulation test software to pass the IT certification exam to become a ITCertKing repeat customers. ITCertKing can provide the leading Microsoft training techniques to help you pass Microsoft certification 070-178 exam.
Exam Code: 070-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2013-12-13
ITCertKing's products can not only help customers 100% pass their first time to attend Microsoft certification 070-178 exam, but also provide a one-year of free online update service for them, which will delivery the latest exam materials to customers at the first time to let them know the latest certification exam information. So ITCertKing is a very good website which not only provide good quality products, but also a good after-sales service.
We all know that in the fiercely competitive IT industry, having some IT authentication certificates is very necessary. IT authentication certificate is a best proof for your IT professional knowledge and experience. Microsoft 070-178 is a very important certification exam in the IT industry and passing Microsoft certification 070-178 exam is very difficult. But in order to let the job position to improve spending some money to choose a good training institution to help you pass the exam is worthful. ITCertKing's latest training material about Microsoft certification 070-178 exam have 95% similarity with the real test. If you use ITCertKing'straining program, you can 100% pass the exam. If you fail the exam, we will give a full refund to you.
070-178 Free Demo Download: http://www.itcertking.com/070-178_exam.html
NO.1 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft 070-178 exam prep 070-178 070-178 exam prep
NO.2 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft test questions 070-178 070-178 answers real questions
NO.3 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft exam dumps 070-178 answers real questions 070-178 exam prep 070-178
NO.4 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft 070-178 070-178 070-178 exam dumps 070-178 demo
NO.5 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft 070-178 070-178 certification
NO.6 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft 070-178 070-178 070-178 070-178 demo
NO.7 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft 070-178 original questions 070-178 070-178 070-178
NO.8 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft practice test 070-178 070-178 certification 070-178
NO.9 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft 070-178 questions 070-178 070-178 070-178
NO.10 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft exam simulations 070-178 exam dumps 070-178 study guide 070-178
ITCertKing offer the latest 000-455 exam material and high-quality JN0-533 pdf questions & answers. Our 9L0-620 VCE testing engine and PMI-100 study guide can help you pass the real exam. High-quality VCAC510 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.
Article Link: http://www.itcertking.com/070-178_exam.html
没有评论:
发表评论